Smart Test Gateway — PoC and MVP product requirements

Version: 0.2 · Date: 10 September 2026
Status: Initial product and delivery proposal for review; implementation has not started.
Architecture baseline: STG 1.5; OTDP 0.3.0; adapter API 1.1; registry/execution 1.0.0; interface 1.1.0; MCP 2026-07-28.

1. Product decision

Build one complete, reusable test-bench workflow before broadening device coverage. The PoC proves software behaviour with simulated devices. The MVP delivers a separately qualified low-voltage hardware workflow, including approved unattended execution. Both demonstrate that a second user can reuse a published integration instead of writing another driver.

The product is a local test gateway with shared device integrations. Its first useful outcome is an operator finding compatible integrations, admitting them to a bench, running an approved test and receiving trustworthy results and recovery information through REST or an AI client using MCP.

Delivery option Trade-off Selection
Simulator-first complete workflow, then one qualified bench Early deterministic fault testing; hardware proof remains a distinct gate Recommended baseline
Hardware-first one-device demo Faster visible instrument control but weak replay/failure evidence and dependency on equipment availability Do not use as the PoC exit criterion
Implement all twelve classes and a public marketplace first Broad scope delays proof of core value Deferred

Selected hardware: FNIRSI DPS-150 is the confirmed first instrument. ESP32 is the provisional controller family; exact board/firmware remains to be selected. See the hardware discovery brief for protocol and qualification gates.

2. Problem and users

Instrument integrations are repeatedly recreated, tests are tied to scripts and particular benches, and an acknowledgement can be mistaken for a verified result. An AI interface increases convenience but must not change device ownership, operating limits or evidence requirements.

Primary users:

  • Test engineer: runs repeatable controller tests, evaluates measurements and diagnoses failures.
  • Integration author: publishes a documented plugin once, with compatibility and evidence that others can evaluate.
  • Bench owner: admits equipment, qualifies protection and controls unattended use.
  • AI-assisted operator: discovers capabilities, starts approved procedures and inspects results through the same authorised core.

Stephen is the product decision owner for this proposal. Engineering, registry and bench qualification owners are roles to assign before their respective milestones; names and physical limits are not invented here.

3. Demonstration journey

  1. A clean gateway discovers a curated registry containing a profile package and two simulated implementations: DC supply and embedded controller.
  2. The engineer reviews compatibility, licence, permissions and simulated evidence, then admits exact releases locally.
  3. The bench owner selects a versioned simulated fixture/policy and approved procedure. Simulation is visibly identified throughout.
  4. The operator starts the procedure through REST, retrieves the same run through MCP and views a concise report.
  5. The procedure configures/enables the simulated supply, obtains supply measurements and numeric controller telemetry, evaluates assertions, disables the supply and verifies the modelled final safe condition.
  6. A deliberately lost response, stale sample, trip or gateway restart produces the defined outcome without an unintended second run.
  7. A second clean installation reuses the same registry packages without modifying plugin source.
  8. For the MVP, replace the simulated devices with selected real equipment, perform qualification, then demonstrate the approved unattended procedure.

Controller assertions use a documented numeric telemetry quantity supported by the chosen DUT. The simulator supplies a specified numeric quantity in its protocol fixture. For an ESP32 reference DUT, a small separately versioned telemetry firmware is included in the MVP work package if suitable firmware does not already exist; it supplies numeric uptime in seconds and explicit identity/correlation. It is not an independent protective controller. The plan does not assume a particular real controller exposes supply voltage, uptime or a boot flag. A Boolean boot assertion would require an explicit execution-contract extension or a separately justified supported numeric measurement; do not silently change types to fit the PoC.

4. Scope by stage

Capability PoC Hardware MVP
Local gateway One Linux host, one bench, one controlling run Same ownership boundary on the qualified host
Device coverage DC PSU and embedded-controller simulator plugins FNIRSI DPS-150 plus a provisionally selected ESP32 fixture; required independent evidence source
Procedure engine Full bounded execution 1.0.0 language; unsupported device actions rejected Same language on the qualified procedure/device set
Registry reuse Curated static registry, exact pins, test trust root, local review, second installation Controlled shared registry with operational signing/recovery and support ownership
Interfaces Twenty REST operations and seventeen MCP tools, with administrative staging limited to the two-plugin bench Same interface; exact tested client/authentication matrix
Identity Local test issuer with validated audience/scopes and separate principals Configured production identity provider and scoped accounts
Protection Faultable simulation; clearly no physical safety claim Qualified independent protection where required, verified sensing and shutdown
Evidence Durable run/request/events, exact-byte documents, scalar datasets and bounded artefact reads Retention/recovery validated on the deployment
Operator experience CLI for setup/discovery; concise report; MCP client demonstration Documented setup, qualification, operation and recovery workflow
Installation Reproducible native Linux service and clean test environment Qualified native service, updates and backup/restore

A full graphical dashboard is not required for either initial exit gate. Reports and CLI must make run outcome, final safety, evidence gaps and simulation status unambiguous. Public account registration, community moderation automation and a marketplace website are deferred; the first central repository is curated.

5. Prioritised requirements

P0 means required for the named stage; P1 means useful only after those gates pass. Architecture obligations are not waived by their omission from this product summary.

ID Priority/stage Requirement Observable acceptance
PRD-01 P0 PoC Reproducible clean setup with locally pinned contracts/dependencies A second documented Linux environment builds and runs the demo without editing source
PRD-02 P0 PoC Discover and reuse compatible packages Second installation resolves the same digests and runs without creating another implementation
PRD-03 P0 PoC Authenticated immutable package admission Tamper, unknown trust, missing dependency, conflict and revoked-package cases reject before activation
PRD-04 P0 PoC Real plugin ABI through simulated transports Both plugins use published factory/context/host services; no simulator-only shortcut bypasses policy or dispatch evidence
PRD-05 P0 PoC One ownership domain and typed admission Competing starts, stale generations, incompatible bindings and unauthorised principals are rejected
PRD-06 P0 PoC Bounded approved procedures All eight step kinds, lexical references, body/protection budgets and invalid predicates behave as specified
PRD-07 P0 PoC Durable run and request identity Dropped start response and identical REST/MCP retries yield one run and one intended dispatch occurrence
PRD-08 P0 PoC Explicit protection and recovery Trip/cancel/timeout/restart tests preserve uncertainty, never reset the protective deadline or automatically resume
PRD-09 P0 PoC Trustworthy measurement and final report Invalid/stale/wrong-unit evidence cannot pass; missing terminal record or unverified safety cannot produce passed
PRD-10 P0 PoC Interface parity and access scope REST/MCP vectors and live client tests agree; cross-bench evidence reads and principal spoofing fail
PRD-11 P0 PoC Registry and network independence during a run Accepted gateway-owned simulated run finishes within policy through client/registry loss
PRD-12 P0 PoC Controlled administration Separate approved change succeeds only at a safe idle boundary; control identity cannot self-approve
PRD-13 P0 MVP Verified real instrument and DUT support Commands, firmware, transport, channel mapping and compatibility supported by source and hardware evidence
PRD-14 P0 MVP Qualified physical operating envelope Fixture identity, limits, sensing, independent protection and shutdown timing have approved measured evidence
PRD-15 P0 MVP Approved unattended operation Normal and applicable fault runs meet the commissioned response bounds without continuous AI/client judgement
PRD-16 P0 MVP Supportable installation and recovery Backup/restore, updates, revocation, identity replacement and operator recovery procedures demonstrated
PRD-17 P1 after MVP Broaden coverage and presentation Additional device classes or GUI work starts only after a prioritised user need and the initial gates

6. Measurable success criteria

The following are proposed product targets, not measured results or electrical safety thresholds:

  • A prepared engineer can complete the documented clean simulated demo in 30 minutes or less, excluding dependency download time; record the actual result.
  • A second engineer can discover/admit the published integrations and repeat the demo in 30 minutes or less, with zero plugin-source changes.
  • 100 consecutive normal simulated runs produce complete, internally consistent evidence and no duplicate dispatch. Use a fixed seed and retain logs.
  • Every applicable fault case in the PoC test matrix has its expected deterministic outcome; no false passed result is tolerated.
  • On the recorded reference host, metadata reads have p95 ≤500 ms and run acceptance has p95 ≤2 s, excluding device execution. Use 100 requests with one active run and two observers. Exceeding a product target triggers profiling/scope review, not relaxed protective timing.
  • The MVP completes 20 consecutive qualified normal hardware runs plus every applicable approved fault test. Twenty runs demonstrate repeatability for this release; they are not a statistical reliability certification.
  • The product owner accepts the reuse and operator journey; the bench/test-safety owner separately accepts physical and unattended qualification.

7. Stage exit gates

G1 — First working slice: Verified local contract/content store plus one simulator plugin can produce a typed measurement through scoped host services. This is internal engineering evidence, not the product PoC.

G2 — PoC exit: PRD-01 through PRD-12 pass with live software, simulated devices, an independently exercised MCP client, curated authenticated registry and second-installation reuse. Fault results and performance measurements are retained. No claim that all twelve classes are implemented.

G3 — Supervised hardware gate: Hardware selection, manuals, firmware, identity, host-provider contracts and physical protection are documented. PRD-13/14 pass before using an energised fixture outside the approved commissioning activity. Simulation approvals cannot authorise hardware.

G4 — MVP exit: PRD-15/16 pass, normal/fault hardware evidence and operational procedures are reviewed, and the unattended procedure is specifically qualified. A successful PoC does not automatically open this gate.

8. Risks and release controls

Risk Delivery response
First equipment/protocol information unavailable Continue simulator PoC; hold hardware tasks at G3
SDK mismatch with MCP 2026-07-28 Early live interoperability task; pin a verified compatible SDK or write a bounded adapter preserving the selected contract
Simulators hide transport ambiguity Faultable transport boundary, dispatch ledger, process-kill tests and real hardware gate
Registry work expands into marketplace development Static curated publishing/discovery first; preserve the trust/metadata contract
Durability/protection timing competes with downloads Separate quotas, bounded single-writer persistence and failure injection; qualify actual response timing
UI or broad class support consumes schedule CLI/report first; two implemented profiles until G2
Draft planning assumptions mistaken for approval Gate records bind actual evidence, owner and exact content digests

9. Inputs still needed

The PSU model is now selected: FNIRSI DPS-150. Hardware planning still needs its exact revision/firmware, the ESP32 board and telemetry firmware, available independent measurement/protection hardware, target Linux host and applicable protocol evidence. These inputs select the first qualified integrations; they do not block the simulator work packages.

Before committing dates: assign engineering/QA/bench owners, confirm available effort and review lead times. This PRD deliberately sets dependency gates rather than unsupported calendar promises. The repository name and proposed layout in the plan are planning choices; no source repository has been created.

10. Product release decision

Approve the PoC on demonstrated reuse, deterministic recovery and honest evidence. Approve the MVP only after separate physical/unattended qualification. Additional device families, fleets, unrestricted scripts, cloud control and public marketplace operations remain outside this release.